
06/03/24
The Northern Ireland Audit Office recently undertook a review of major capital projects in Northern Ireland, following on from a previous report in 2019, which then identified a number of issues of concerns and recommendations for improvement. These recommendations were revisited in this updated report, and the outcomes are concerning. This is a summary of the key points with a link to the main report below.
Link to full report: Major Capital Projects – Follow-up Report | Northern Ireland Audit Office (niauditoffice.gov.uk)
Key Facts:
In the period April 2019 to August 2023:
While accepting the complexity of the majority capital projects, and the negative effective of a lack of multi-year budgeting, the NIAO reached the conclusion that departments are not achieving value for money in the delivery of major capital projects. Issues identified previously have largely persisted, and delays and cost overruns continue to occur frequently throughout the major capital projects portfolio. The following recommendation was made ‘However, given the lack of substantive progress since our last report, we are of the view that immediate action is needed to prevent further cost overruns and delays’.
Over the past ten years a series of reviews by the SIB, CBI and OECD have highlighted significant weaknesses in the commissioning and delivery system for major capital projects in Northern Ireland, and the need for substantial reform. These, as well as the NIAO reports, have so far failed to stimulate significant improvement, and key stakeholders have expressed frustration and disappointment with the perceived reluctance to embrace change.
Key Projects and Current Status:
| A5 upgrade the A5 Western Transport Corridor | Delayed. Department considering PAC findings |
| A6 – This project involved upgrading the A6 element of the Northwestern Transport Corridor connecting Belfast to Londonderry | Substantially complete |
| Belfast Rapid Transit | Complete |
| Maternity and Children’s Hospital | Maternity is substantively built it is not operational. children’s hospital now expected to be completed by 2029. |
| The Northern Ireland Fire and Rescue Service Learning and Development Centre at Cookstown | Partially completed |
| Regional Stadia Programme and Sub-Regional Stadia Programme for Football | Partially completed although key elements not progressed |
| Belfast Transport Hub | Work ongoing |
Other projects such as the new Ulster University campus, the Strule Shared Education Campus, Critical Care Centre at the Royal Victoria Hospital and the Lisburn and Newry
Primary Community Care Centres have also been analysed and demonstrate the same type of concerns.
Recommendations for change include: